Bug Tracker - Ready
All the testers and developers are now setup as users in Bug Tracker.
Everyone should test to make sure they can access and login to the server.
I asked Dan H. to make sure everything is working ok - adding bugs, reporting, etc.
Monday, January 26, 2009
Goals for the Week 1/26
1. Find out what happen to the iPaq device.
2. Get the TPS Server installed
3. Contact Blackberry about VPN issues
4. Basecamp Presentation on Friday
2. Get the TPS Server installed
3. Contact Blackberry about VPN issues
4. Basecamp Presentation on Friday
Thursday, January 22, 2009
Week of Jan 19th through Jan 23
- I asked the IT department at Abington to try and get the Blackberry VPN working. They were unable to get it online. We need to contact Blackberry and PSU to compare the differences between the iPhone device and the Blackberry.
- The TPS Server is almost ready it just needs some of the data cleaned off. It should be ready on Friday.
- Kinjal is still determining the scope of the changes needed by Jim to the call center structure.
- Mike Kucklinca is the new QA manager at TPS and will be involved with the mobile project. His email address is MKucklinca@tpayment.com.
- I would like to publish the light PCI guidelines to the class to review.
- The iPaq Pad unit should be here by Friday I need to order the VPN software to connect to the Abington network.
- I will add all the users to basecamp that were requested.